Showing posts with label Nuclear Power Plant in Czech. Show all posts
Showing posts with label Nuclear Power Plant in Czech. Show all posts

Dukovany Nuclear Power Plant

The Dukovany Nuclear Power Plant is a nuclear power plant (NPP) near Dukovany, a village in the Czech Republic.

It was the first NPP in what is now the Czech Republic (the Bohunice Nuclear Power Plant in what is now Slovakia was constructed in 1958) and is situated 30 km from the city of Třebíč, near Dalešice Dam, where the NPP sources its water supply. In 1970 Czechoslovakia and the Soviet Union ratified a contract for construction of two NPPs. Actual construction work began four years later. From 1985 to 1987, four power units with pressurized water reactors were commissioned. All four are still in operation.

In 1994, a tourist centre was opened at the site.

Dukovany Nuclear Power Plant is owned and operated by CEZ Group. CEZ recently tendered for new reactor construction, including an option for building a fifth reactor block at Dukovany. The winner of the tender will be declared in 2011.

Technical data

The Dukovany Nuclear Power Plant has four reactors. As of May 2009 CEZ reported turbine generator output (gross capacity) as listed below. Net capacity is a baseline estimate only.

Unit Type Net capacity Gross capacity Initial criticality Grid date
1 VVER 440/V213 >427 MWe 464 MWe Feb 1985 Aug 1985
2 VVER 440/V213 >427 MWe 466 MWe Jan 1986 Sep 1986
3 VVER 440/V213 >427 MWe 502 MWe Oct 1986 May 1987
4 VVER 440/V213 >427 MWe 465 MWe Jun 1987 Dec 1987

In 2005, Unit 3 was upgraded to 456 MWe gross capacity, and the same upgrade was made to Unit 1 and Unit 4 in 2007. Unit 3 was further upgraded in 2009 to 500MWe. In total an extra 240 MWe of capacity has been or will be added before 2013 in a comprehensive program of improvements including steam plant replacement, addition of instrumentation and fuel changes.

Cooling Towers

Dukovany Nuclear Power Station has 8 cooling towers, each 125 metres tall.

Meteorological Tower

West of the facility at 49°5'42.89"N, 16°8'5.44"E, there is a 136 metre tall guyed tower for monitoring air radioactivity.

Power distribution

The powerlines leaving Dukovany Nuclear Power Station are mainly installed on delta type pylons. They run to Slavetice substation situated at 49°6'15" N and 16°7'10" E. At this substation the powerline to Dürnrohr in Austria starts.

Plant owner CEZ plans to install a district heating circuit to supply heat to homes and businesses in Brno. A pipeline over 40 kilometres in length could be installed after regional officials have considered CEZ's environmental impact statement for the project, submitted in July 2010.

Dukovany Nuclear Power Plant
Country Czech Republic
Construction began 1974
Construction cost Kčs 25 billion
Operator(s) CEZ Group

Reactor information
Reactors operational 1 x 464 MW
1 x 466 MW
1 x 502 MW
1 x 465 MW
Reactor type(s) VVER 440

Power generation information
Annual generation 13,396 GW·h
Net generation 279,193 GW·h

Temelín Nuclear Power Plant

Temelín Nuclear Power Plant (Jaderná elektrárna Temelín, abbreviation JETE) is located near Temelín, a small village in the Czech Republic. Temelín NPP is owned by ČEZ Group, which employs 1000 workers at this site. The adjacent castle Vysoký Hrádek serves as an information centre.

Technical data

Station Reactor type Net capacity Gross capacity Initial criticality Grid date Exp. shutdown
Temelín 1 VVER 1000/320 963 MWe 1013 MWe Dec 2000 Jun 2002 2042
Temelín 2 VVER 1000/320 963 MWe 1013 MWe Dec 2002 Apr 2003 2043

The plant has four cooling towers. Each tower has a height of 150 metres (490 ft), a diameter of 130 metres (430 ft), and an external wall surface area of 44,000 square metres (470,000 sq ft).

The reactor vessel contains 163 fuel assemblies; a single assembly has 313 fuel rods. There are 61 control rods.

New reactors in Temelin Nuclear Power Plant

Plans to build all four original reactors were reopened in 2005. In 2007 planning was suspended because a new government agreed not to promote nuclear energy; a Green Party was a member of the coalition government. However, in July 2008 ČEZ requested the Ministry of the Environment conduct an environmental impact assessment for two additional reactors. In 2009 regional approval was granted for the new build. ČEZ plans to begin construction in 2013, with completion of the first block in 2020. In August 2009, ČEZ sought bids for two pressurized water reactors (PWRs). As of 2010 the companies bidding for the project are Areva, Westinghouse Electric Company, and a consortium of Skoda JS, Atomstroyexport and Gidropress. The winner of the tender will be made public in 2011. Shortly after Fukushima I nuclear accidents, Prime Minister Petr Nečas announced that the construction of new reactors will continue according to the original plans.

Temelín Nuclear Power Station
Country Czech Republic
Status Operational
Construction began 1981
Commission date June 10, 2002
Construction cost 98.6 billion CZK
Operator(s) ČEZ, a. s.
Constructor(s) Westinghouse, Skoda JS

Reactor information
Reactors operational 2 x 963 MW
Reactor type(s) VVER 1000/320 PWRs

Power generation information
Annual generation 11,377 GW·h
Net generation 51,518 GW·h