The Cruas Nuclear Power Station is a Nuclear power plant located in Cruas and Meysse communes, Ardèche next to the Rhône River in France. The site is 35km north of Tricastin Nuclear Power Center and near the town of Montélimar.

The site contains 4 pressurized water reactors of 900 MW each, totaling 3600 MW total. The construction began in 1978, the reactors were built between 1983 and 1984.

The power station accounts for 4 to 5% of the electric energy production in France, and 40% of the annual usage by the Rhone-Alps area. The site employs about 1,200 workers and has an area of 148 hectares. Cooling water comes from the Rhône river.

On 1 December 2009 reactor 4 was shut down after vegetation blocked the intake of the cooling system. The nuclear safety authority Autorité de sûreté nucléaire (ASN) classified the incident as level 2 on the International Nuclear Event Scale

In 1991 it was decided by the owners of the plant to carry out a Mural project on the cooling towers focusing on the topic of ecology. Author of the mural on the Tignes dam, Jean-Marie Pierret was selected to design the painting, 9 mountaineers helped to actually paint the structure. The painting reflects the basics of Water and Air and is titled Aquarius, and was inaugurated in 2005. It took 8,000 working hours and 4,000 liters of paint to complete the project.

Cruas Nuclear Power Plant
Data
Country France
Operator EDF
Built 1978
Start of commercial operation April 29, 1983
Reactors
Reactors active 4 (3,824 MW)
Power
Total power generation in 2006 23,241 GW·h
Average annual generation (last 5 yrs) 24,244 GW·h
Net generation 513,867 GW·h